Sprint Pulse
Product Pulse — Team 2 ADS Q2 W22 - 01-05 Iunie
Planned sprint ADS Q2 W22 - 01-05 Iunie • planning snapshot + end-of-sprint outcome snapshot
This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.
Download DOCX
Executive summary
Yellow. The sprint closed 4 of 16 visible items, including 1 Stories, 1 Tasks, and 2 Bugs. Product movement was real, but the sprint was still noisy: 2 items entered after planning and 0 of them were closed. The main misses were concentrated in 12 carryovers.
Top-line metrics
| Metric | Value | How to read it |
|---|
| Visible sprint items | 16 | Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses |
| Delivered items | 4 | Items whose final outcome bucket is Done |
| Carry overs | 12 | Items not closed at sprint review |
| Delivered mix | 1 / 1 / 2 | Stories / Tasks / Bugs delivered |
| Entry kind mix | 14 / 2 / 0 | Planned / Added during sprint / Stretch visible |
| Readiness mix | 7 / 9 / 0 | Ready / At risk / Not Ready across the normalized sprint fact base |
| Progress items behaving as intended | 1/2 | Progress items were expected not to finish in this sprint |
Stories done (1)
Below are the items marked Done in the sprint review snapshot, grouped by work-item type.
Carry overs / not delivered (12)
Blocker / miss pattern
| Metric | Value | How to read it |
|---|
| Partial completion | 4 | Carryovers blocked by partial completion |
| Dependency / competing work | 4 | Delivery slipped because attention or dependency landed elsewhere |
| Not started | 2 | Committed item never really got underway |
Data-quality caveats
This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.
1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.
Traceability / drill-down
| Report element | How to drill down | Traceability mechanism |
|---|
| Delivered Stories / Tasks / Bugs | Click the section count rows | Snapshot-exact JQL by issuekey list |
| Carry overs / not delivered | Click the Carry overs count | Snapshot-exact JQL by issuekey list |
| Miss pattern summary | Click each miss-pattern count | Snapshot-exact JQL by issuekey list |
Snapshot and fact-base list links
| Snapshot / movement | Issue count | Calculation | Link |
|---|
| Planning snapshot raw list | 15 | Frozen planning export before metric exclusions | Open JQL |
| Sprint review / outcome snapshot raw list | 17 | Frozen review export before metric exclusions | Open JQL |
| Normalized sprint fact base | 16 | Deduplicated union used by metrics after canceled/cancelled exclusions | Open JQL |
| Metric planning baseline | 14 | Non-canceled issue keys present in the frozen planning snapshot | Open JQL |
| Metric outcome snapshot | 16 | Non-canceled issue keys present in the frozen sprint-review snapshot | Open JQL |
| Planned and still present at review | 14 | planning_snapshot_present = true and outcome_snapshot_present = true | Open JQL |
| Added after planning | 2 | planning_snapshot_present = false and outcome_snapshot_present = true | Open JQL |
| Planned but missing from review | 0 | planning_snapshot_present = true and outcome_snapshot_present = false | Open JQL |
| Metric-excluded canceled/cancelled rows | 1 | Rows preserved in audit but excluded from every numerator and denominator | Open JQL |
Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.
Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.
Metric register addendum
| Metric | Value | Formula | Numerator / denominator | Denominator evidence |
|---|
| Visible sprint items | 16 | all rows in the outcome snapshot | 16/16 | Open denominator JQL |
| Delivered items | 4 | rows whose Sprint Outcome is Done | 4/16 | Open denominator JQL |
| Carry overs | 12 | rows whose Sprint Outcome is Carry Over or remained open in review | 12/16 | Open denominator JQL |
| Stories done | 1 | done items where issue type = Story | 1/4 | Open denominator JQL |
| Tasks done | 1 | done items where issue type = Task | 1/4 | Open denominator JQL |
| Bugs done | 2 | done items where issue type = Bug | 2/4 | Open denominator JQL |
| Entry kind mix | 14 / 2 / 0 | Planned / Added / Stretch counts across all visible sprint items | 16/16 | Open denominator JQL |
| Readiness mix | 7 / 9 / 0 | Ready / At risk / Not Ready counts across all visible sprint items | 16/16 | Open denominator JQL |
| Progress items behaving as intended | 1/2 | progress-intent items that carried as intended ÷ all progress-intent committed items | 1/2 | Open denominator JQL |
| Partial completion misses | 4 | carryover items whose miss reason is Partial completion | 4/12 | Open denominator JQL |
| Dependency / competing work misses | 4 | carryover items whose miss reason is Dependency delay | 4/12 | Open denominator JQL |
| Not-started misses | 2 | carryover items whose miss reason is Not started | 2/12 | Open denominator JQL |
Evidence artifacts
Use these files when you need to validate the exact rows and formulas behind a pulse claim.