Sprint Pulse

Product Pulse — Team 2 ADS Q3 W30 - 27-31 Jul

Planned sprint ADS Q3 W30 - 27-31 Jul • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 4 of 7 visible items, including 0 Stories, 1 Tasks, and 3 Bugs. Product movement was real, but the sprint was still noisy: 3 items entered after planning and all of them were closed. The main misses were concentrated in 3 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items7Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items4Items whose final outcome bucket is Done
Carry overs3Items not closed at sprint review
Delivered mix0 / 1 / 3Stories / Tasks / Bugs delivered
Entry kind mix4 / 3 / 0Planned / Added during sprint / Stretch visible
Readiness mix2 / 4 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended2/2Progress items were expected not to finish in this sprint

Stories done (0)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered

Tasks done (1)

Jira itemHow entered
ADS-8327 — Optimizare Distribuire Stire & ImprovementsPlanned

Bugs done (3)

Jira itemHow entered
ADS-8321 — Notificari pentru elevii ce au terminat in anii trecutiAdded
ADS-8333 — [Admitere] - Datele extrase din diploma de bacalaureat nu se populează în tabelul de candidațiAdded
ADS-8336 — [Admin scoli / setari unitati - apare Petre Andrei]Added

Carry overs / not delivered (3)

Jira itemWhy it carried
ADS-5654 — Story — [UPA,UPG, Asachi] Taxe școlarizarePartial completion
ADS-6159 — Story — Notification Center for MobilePartial completion
ADS-6675 — Story — [Financiar] - Managementul penalitatilorPartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion3Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started0Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

2 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list4Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list7Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base7Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline4Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot7Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review4planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning3planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows0Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items7all rows in the outcome snapshot7/7Open denominator JQL
Delivered items4rows whose Sprint Outcome is Done4/7Open denominator JQL
Carry overs3rows whose Sprint Outcome is Carry Over or remained open in review3/7Open denominator JQL
Stories done0done items where issue type = Story0/4Open denominator JQL
Tasks done1done items where issue type = Task1/4Open denominator JQL
Bugs done3done items where issue type = Bug3/4Open denominator JQL
Entry kind mix4 / 3 / 0Planned / Added / Stretch counts across all visible sprint items7/7Open denominator JQL
Readiness mix2 / 4 / 1Ready / At risk / Not Ready counts across all visible sprint items7/7Open denominator JQL
Progress items behaving as intended2/2progress-intent items that carried as intended ÷ all progress-intent committed items2/2Open denominator JQL
Partial completion misses3carryover items whose miss reason is Partial completion3/3Open denominator JQL
Dependency / competing work misses0carryover items whose miss reason is Dependency delay0/3Open denominator JQL
Not-started misses0carryover items whose miss reason is Not started0/3Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.