Sprint Pulse

Product Pulse — Team 2 ADS Q3 W32 - 10-14 Aug

Planned sprint ADS Q3 W32 - 10-14 Aug • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 4 of 14 visible items, including 2 Stories, 1 Tasks, and 1 Bugs. Product movement was real, but the sprint was still noisy: 2 items entered after planning and 1 of them were closed. The main misses were concentrated in 10 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items14Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items4Items whose final outcome bucket is Done
Carry overs10Items not closed at sprint review
Delivered mix2 / 1 / 1Stories / Tasks / Bugs delivered
Entry kind mix12 / 2 / 0Planned / Added during sprint / Stretch visible
Readiness mix8 / 6 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended4/4Progress items were expected not to finish in this sprint

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-8071 — Teste automate flow SubscripțiiPlanned
ADS-8342 — [AI - MCP] - PipeworkPlanned

Tasks done (1)

Jira itemHow entered
ADS-8468 — Drop AZURE models and replace with BedrockAdded

Bugs done (1)

Jira itemHow entered
ADS-8216 — [Admitere] - Nu apare descrierea Raportului in modalPlanned

Carry overs / not delivered (10)

Jira itemWhy it carried
ADS-5654 — Story — [UPA,UPG, Asachi] Taxe școlarizarePartial completion
ADS-6159 — Story — Notification Center for MobilePartial completion
ADS-7251 — Story — Mutarea subscriptii de pe recurenta An scolar pe recurenta an calendaristicPartial completion
ADS-8255 — Bug — [BE][Admission] - Problema la aplicare status pregatit pe un candidat admiterePartial completion
ADS-8339 — Story — ToolsPartial completion
ADS-8383 — Story — [BE] - Local Cache BillingPartial completion
ADS-8428 — Task — Mng Penalitatilor BugsPartial completion
ADS-8482 — Task — [BE] Replace audit interceptor for the AI projectNot started
ADS-8497 — Task — [BE] Integrate the AI service with the MCP serverPartial completion
ADS-8499 — Task — Sync coduri SirutaPartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion8Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

4 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1010 issues in the planning snapshot
Sprint review / outcome snapshot raw list1414 issues in the Friday review snapshot
Normalized sprint fact base1414 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.