Sprint Pulse

Product Pulse — Team 2 ADS Q3 W33 - 17-21 Aug

Planned sprint ADS Q3 W33 - 17-21 Aug • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 4 of 17 visible items, including 0 Stories, 3 Tasks, and 1 Bugs. Product movement was real, but the sprint was still noisy: 1 items entered after planning and 0 of them were closed. The main misses were concentrated in 13 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items17Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items4Items whose final outcome bucket is Done
Carry overs13Items not closed at sprint review
Delivered mix0 / 3 / 1Stories / Tasks / Bugs delivered
Entry kind mix16 / 1 / 0Planned / Added during sprint / Stretch visible
Readiness mix9 / 8 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended2/2Progress items were expected not to finish in this sprint

Stories done (0)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered

Tasks done (3)

Jira itemHow entered
ADS-8428 — Mng Penalitatilor BugsPlanned
ADS-8482 — [BE] Replace audit interceptor for the AI projectPlanned
ADS-8497 — [BE] Integrate the AI service with the MCP serverPlanned

Bugs done (1)

Jira itemHow entered
ADS-8255 — [BE][Admission] - Problema la aplicare status pregatit pe un candidat admiterePlanned

Carry overs / not delivered (13)

Jira itemWhy it carried
ADS-5654 — Story — [UPA,UPG, Asachi] Taxe școlarizarePartial completion
ADS-7251 — Story — Mutarea subscriptii de pe recurenta An scolar pe recurenta an calendaristicPartial completion
ADS-7279 — Task — [Billing] - Implementare Stripe + Apple pay + Google payPartial completion
ADS-7578 — Bug — Cache_redis_sentinel.php: Redis token-cache connection refusals turn GET /api/v2/fisiere/view into HTTP 500 - 254 hits/24hNot started
ADS-7659 — Story — [Abonamente] - Nu pot selecta România din secțiunea de publicare, și nu mai apar pachetele pe site-ul publicPartial completion
ADS-7849 — Story — Stergere date S3Not started
ADS-8223 — Bug — [Prod][AWS][ingress] POST /api/v2/fisiere/upload maps backend 400 to HTTP 500 - 10/72hNot started
ADS-8339 — Story — ToolsPartial completion
ADS-8383 — Story — [BE] - Local Cache BillingPartial completion
ADS-8499 — Task — Sync coduri SirutaPartial completion
ADS-8500 — Task — [AI] - Shared folder, logging, tracingPartial completion
ADS-8501 — Task — S3: Ștergere variabile OSS vechi și verificat că totul merge bineNot started
ADS-8544 — Bug — Billing invoice export can timeout/OOM and silently truncate large result setsLate start / sequencing

Blocker / miss pattern

MetricValueHow to read it
Partial completion8Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started4Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

2 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1616 issues in the planning snapshot
Sprint review / outcome snapshot raw list1717 issues in the Friday review snapshot
Normalized sprint fact base1717 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.