Product Pulse — University ADS Q2 W22 - 01-05 Iunie

Planned sprint ADS Q2 W22 - 01-05 Iunie • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 7 of 16 visible items, including 2 Stories, 3 Tasks, and 2 Bugs. Product movement was real, but the sprint was still noisy: 4 items entered after planning and 1 of them were closed. The main misses were concentrated in 9 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items16Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items7Items whose final outcome bucket is Done
Carry overs9Items not closed at sprint review
Delivered mix2 / 3 / 2Stories / Tasks / Bugs delivered
Entry kind mix11 / 4 / 1Planned / Added during sprint / Stretch visible
Readiness mix5 / 9 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended2/3Progress items were expected not to finish in this sprint

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7132 — [FE/BE] - Gestiunea restantierilorPlanned
ADS-7476 — [UNI][MAIN][Plan invatamant] - Teste automate Plan invatamant (adaugare, editare, import) E2EPlanned

Tasks done (3)

Jira itemHow entered
ADS-7472 — [FE/BE][UNMB] - Actualizare a structurii (serii, grupe) astfel încât afișarea să respecte ordinea din fișierele transmisePlanned
ADS-7635 — [FE/BE][UNMB] - Posibilitatea introducerii notelor cu zecimalePlanned
ADS-7729 — Îmbunătățirea procesului pentru import Excel studenți V2Planned

Bugs done (2)

Jira itemHow entered
ADS-7742 — [FE/BE][Cazari] - Filtrul dupa camera si camin nu returneaza studentiiPlanned
ADS-7751 — [BE][Catalog- Note discipline-Asachi] - Notele introduse nu sunt afișate, iar în catalog apare valoarea „null”Added

Carry overs / not delivered (9)

Jira itemWhy it carried
ADS-7375 — Story — [BE/FE] - Disciplinele in EN pentru programele de studiu din ENPartial completion
ADS-7388 — Bug — docgen2-api: gradebook view/download endpoints return HTTP 500 - 15 hits/FridayNot started
ADS-7495 — Story — [FE/BE][Adeverinte absolvire] - Creare Probe evaluarePartial completion
ADS-7496 — Story — [FE/BE][Adeverinte absolvire] - Probe&medie pe situatie scolaraPartial completion
ADS-7534 — Story — [FE/BE][Adeverinte absolvire] - Flow generare adeverintePartial completion
ADS-7666 — Bug — accommodations-api: shared HTTP 500 burst on POST /api/v2/accommodations/dorms/list and related endpoints - 16 hits/20mBug / rework pressure
ADS-7688 — Bug — [BE] [Studenti] [Muzica]- Studentul nu este unificat pe baza CNP-ului la importNot started
ADS-7708 — Bug — [BE] - Personal universitar: Numele nu se actualizeaza corect dupa editareNot started
ADS-7740 — Story — [TDD][Generare Adeverințe] - Creare document tehnicNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion3Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started2Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

2 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list12Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list16Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base16Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline12Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot16Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review12planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning4planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows0Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items16all rows in the outcome snapshot16/16Open denominator JQL
Delivered items7rows whose Sprint Outcome is Done7/16Open denominator JQL
Carry overs9rows whose Sprint Outcome is Carry Over or remained open in review9/16Open denominator JQL
Stories done2done items where issue type = Story2/7Open denominator JQL
Tasks done3done items where issue type = Task3/7Open denominator JQL
Bugs done2done items where issue type = Bug2/7Open denominator JQL
Entry kind mix11 / 4 / 1Planned / Added / Stretch counts across all visible sprint items16/16Open denominator JQL
Readiness mix5 / 9 / 0Ready / At risk / Not Ready counts across all visible sprint items16/16Open denominator JQL
Progress items behaving as intended2/3progress-intent items that carried as intended ÷ all progress-intent committed items2/3Open denominator JQL
Partial completion misses3carryover items whose miss reason is Partial completion3/9Open denominator JQL
Dependency / competing work misses0carryover items whose miss reason is Dependency delay0/9Open denominator JQL
Not-started misses2carryover items whose miss reason is Not started2/9Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.