Sprint Pulse

Product Pulse — University ADS Q3 W30 - 27-31 Jul

Planned sprint ADS Q3 W30 - 27-31 Jul • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 10 of 21 visible items, including 1 Stories, 0 Tasks, and 9 Bugs. Product movement was real, but the sprint was still noisy: 3 items entered after planning and all of them were closed. The main misses were concentrated in 11 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items21Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items10Items whose final outcome bucket is Done
Carry overs11Items not closed at sprint review
Delivered mix1 / 0 / 9Stories / Tasks / Bugs delivered
Entry kind mix16 / 3 / 2Planned / Added during sprint / Stretch visible
Readiness mix4 / 17 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended3/3Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7952 — [Burse] - US1 - Implementare mecanism AtributePlanned

Tasks done (0)

Jira itemHow entered

Bugs done (9)

Jira itemHow entered
ADS-7666 — accommodations-api: shared HTTP 500 burst on POST /api/v2/accommodations/dorms/list and related endpoints - 16 hits/20mPlanned
ADS-8111 — [FE/BE] - In centralizator note nu apare numele unei disciplinePlanned
ADS-8134 — [BE-PHP] - Obligatii generate pentru studenti decazatiPlanned
ADS-8147 — [BE] - Nu apar studentii pe sesiunea 2Planned
ADS-8286 — [FE/BE/] - Lipsa nota in catalog pentru studentul Luca-Popa M. MihaiPlanned
ADS-8317 — [Cazari] - Sold gresit in obligatia de plata fata de fisa studentuluiPlanned
ADS-8318 — [FE] - Eroare la descarcarea unor documente din mesaje expediateAdded
ADS-8349 — [Prod][AWS][uni-api] Student search export returns 500 on mixed-collation COALESCEAdded
ADS-8371 — [Prod][AWS][uni-api] Student create leaves disciplines unassigned when AcademicPlan is missing - 2 errors/72hAdded

Carry overs / not delivered (11)

Jira itemWhy it carried
ADS-6142 — Story — [Registre Matricole] -US1.1 Creare volume si asociere studenti incadratiPartial completion
ADS-6438 — Task — [BE][UNI] - Sincronizare ID-uri Ani universitari/scolari - UNI/preuni - masterPartial completion
ADS-7534 — Story — [FE/BE][Adeverinte absolvire] - Flow generare adeverinteDependency delay
ADS-7535 — Story — [FE] - Download Adeverinta de absolvireDependency delay
ADS-7906 — Story — [FE/BE] - Config -posibilitatea setarii mediei ca fiind confirmataPartial completion
ADS-8023 — Story — [BE/FE][Adeverinte] Permisiuni &feature flagsPartial completion
ADS-8058 — Story — [BE/FE][UNI] - Generare serii si ani universitari bulkPartial completion
ADS-8159 — Story — [Burse] - US2 - Configurare bugete, PanouPartial completion
ADS-8176 — Story — [State de functii] - RapoarteNot started
ADS-8254 — Bug — [PROD] - In sectiunea de Roluri si permisiuni apar denumiri de director, elevi, parintiDependency delay
ADS-8326 — Bug — [BE-PHP][Cazari] - La decazare soldurie apar incorect fata de fisa studentilorPriority Change

Blocker / miss pattern

MetricValueHow to read it
Partial completion6Carryovers blocked by partial completion
Dependency / competing work3Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

Snapshot / movementIssue countCalculationLink
Planning snapshot raw list18Frozen planning export before metric exclusionsOpen JQL
Sprint review / outcome snapshot raw list21Frozen review export before metric exclusionsOpen JQL
Normalized sprint fact base21Deduplicated union used by metrics after canceled/cancelled exclusionsOpen JQL
Metric planning baseline18Non-canceled issue keys present in the frozen planning snapshotOpen JQL
Metric outcome snapshot21Non-canceled issue keys present in the frozen sprint-review snapshotOpen JQL
Planned and still present at review18planning_snapshot_present = true and outcome_snapshot_present = trueOpen JQL
Added after planning3planning_snapshot_present = false and outcome_snapshot_present = trueOpen JQL
Planned but missing from review0planning_snapshot_present = true and outcome_snapshot_present = falseOpen JQL
Metric-excluded canceled/cancelled rows0Rows preserved in audit but excluded from every numerator and denominatorOpen JQL

Planning and outcome are separate frozen moments. Raw snapshot counts can be larger than metric counts because canceled/cancelled rows stay in audit but leave all metric denominators.

Added after planning is snapshot-based: present in the outcome snapshot and absent from the planning snapshot. Planned but missing from review shows items that left the sprint snapshot before review.

Metric register addendum

MetricValueFormulaNumerator / denominatorDenominator evidence
Visible sprint items21all rows in the outcome snapshot21/21Open denominator JQL
Delivered items10rows whose Sprint Outcome is Done10/21Open denominator JQL
Carry overs11rows whose Sprint Outcome is Carry Over or remained open in review11/21Open denominator JQL
Stories done1done items where issue type = Story1/10Open denominator JQL
Tasks done0done items where issue type = Task0/10Open denominator JQL
Bugs done9done items where issue type = Bug9/10Open denominator JQL
Entry kind mix16 / 3 / 2Planned / Added / Stretch counts across all visible sprint items21/21Open denominator JQL
Readiness mix4 / 17 / 0Ready / At risk / Not Ready counts across all visible sprint items21/21Open denominator JQL
Progress items behaving as intended3/3progress-intent items that carried as intended ÷ all progress-intent committed items3/3Open denominator JQL
Partial completion misses6carryover items whose miss reason is Partial completion6/11Open denominator JQL
Dependency / competing work misses3carryover items whose miss reason is Dependency delay3/11Open denominator JQL
Not-started misses1carryover items whose miss reason is Not started1/11Open denominator JQL

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.