Sprint Pulse

Product Pulse — University ADS Q3 W36 - 07-11 Sep

Planned sprint ADS Q3 W36 - 07-11 Sep • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 15 of 24 visible items, including 2 Stories, 3 Tasks, and 9 Bugs. Product movement was real, but the sprint was still noisy: 6 items entered after planning and all of them were closed. The main misses were concentrated in 9 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items24Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items15Items whose final outcome bucket is Done
Carry overs9Items not closed at sprint review
Delivered mix2 / 3 / 9Stories / Tasks / Bugs delivered
Entry kind mix18 / 6 / 0Planned / Added during sprint / Stretch visible
Readiness mix6 / 15 / 2Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended6/6Progress items were expected not to finish in this sprint

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-8706 — [BE/FE]Cazari - Contract nou perioada didacticaAdded
ADS-8722 — [BE/FE] [State de functii] Configurare nr semigrupe, filtru departament in planul de invatamantAdded

Tasks done (3)

Jira itemHow entered
ADS-8448 — [BE] [State de Functii] Permisiuni dedicate modulAdded
ADS-8579 — [UNI][FE][BE] Permisune Acces secțiunea DocumentePlanned
ADS-8665 — [BE/FE][State de functii]Refactor reduceri aplicate pentru functia de conducereAdded

Bugs done (9)

Jira itemHow entered
ADS-8509 — Universitatea Petre Andrei- nu se afiseaza informatiile din modulul Statistici si rapoartePlanned
ADS-8534 — Asachi - Nu afiseaza an de studiu pentru studentii din anul 1 (2025-2026)din situatie scolaraPlanned
ADS-8597 — [Asachi] - nu se salveaza echivalarea disciplinei Educatie fizica si sportAdded
ADS-8632 — [Prod][TUIASI][uni-api] Missing disciplina.idDepartament causes catalog status HTTP 500 - 1,042 errorsPlanned
ADS-8652 — [Asachi] - Modificare numar credite si inchidere catalogPlanned
ADS-8681 — [Prod][TUIASI][Web] Certificate list uses unsupported MariaDB JSON operator and returns HTTP 500Planned
ADS-8683 — [Prod][AWS][Uni] Missing workload_percentage tenant migration breaks position creationPlanned
ADS-8685 — [Prod][AWS][uni-api] Missing mentiune migration breaks student discipline listPlanned
ADS-8696 — [Asachi] - modificare student in platformaAdded

Carry overs / not delivered (9)

Jira itemWhy it carried
ADS-7559 — Story — [UPG] - Adeverinte de studentPartial completion
ADS-8160 — Story — [Burse] - US3 - Configurare bursePartial completion
ADS-8161 — Story — [Burse] - US4 - Alocare bursePartial completion
ADS-8164 — Story — [Burse] - US6 - RapoarteNot started
ADS-8179 — Story — [Registre Matricole] - US2 Incarcare atribute studenti pentru popularea registrelor matricolePartial completion
ADS-8326 — Bug — [BE-PHP][Cazari] - La decazare soldurie apar incorect fata de fisa studentilorBreakdown issue
ADS-8593 — Bug — [Prod][TUIASI][legacy-web] Admin edit reads missing suppressAdminEvent flag - 2 warnings/72hNot started
ADS-8667 — Story — [FE/BE] Lista imbunatatiri dupa demo 3.09.26Missing from outcome snapshot
ADS-8682 — Bug — [Prod][TUIASI][Accommodations] Dependency failures cause report and list HTTP 500 burstNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion4Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started3Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

6 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1818 issues in the planning snapshot
Sprint review / outcome snapshot raw list2323 issues in the Friday review snapshot
Normalized sprint fact base2424 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.