Sprint Pulse

Product Pulse — University ADS Q3 W37 - 14-18 Sep

Planned sprint ADS Q3 W37 - 14-18 Sep • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 11 of 21 visible items, including 1 Stories, 2 Tasks, and 8 Bugs. Product movement was real, but the sprint was still noisy: 10 items entered after planning and all of them were closed. The main misses were concentrated in 10 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items21Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items11Items whose final outcome bucket is Done
Carry overs10Items not closed at sprint review
Delivered mix1 / 2 / 8Stories / Tasks / Bugs delivered
Entry kind mix11 / 10 / 0Planned / Added during sprint / Stretch visible
Readiness mix9 / 10 / 2Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended6/6Progress items were expected not to finish in this sprint

Stories done (1)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-8706 — [BE/FE]Cazari - Contract nou perioada didacticaAdded

Tasks done (2)

Jira itemHow entered
ADS-8764 — [Asachi][BE]Cazari - Data start perioada didacticaPlanned
ADS-8803 — [Universitatea de Muzica Bucuresti] - activare modul CazariAdded

Bugs done (8)

Jira itemHow entered
ADS-8597 — [Asachi] - nu se salveaza echivalarea disciplinei Educatie fizica si sportAdded
ADS-8670 — [Asachi] - Eroare salvare/afișare calificativ in catalog la disciplina Practica de SpecialitateAdded
ADS-8678 — [Petre Andrei] - Posibilitatea de a edita grupa studentului ulterior înrolării (când grupa a fost lăsată necompletată)Added
ADS-8767 — [Prod][TUIASI][uni-api] Academic-summary worker loops on NULL requestedAt queue rows - 1,411 failures/72hAdded
ADS-8770 — [Cazari] - nu se poate descarca fisa studentilor si nici borderoul de incasariAdded
ADS-8783 — [FE][Asachi] Permisiune editare din Rol manager a structurii universitare pentru anii urmatori anului activAdded
ADS-8796 — [BE] [Asachi] Echivalari ErasmusAdded
ADS-8824 — [TUIASI][Cazari] accommodations-events recycles after one export event, both replicas stuck in CrashLoopBackOff at 5m backoff since image ab0d59cdAdded

Carry overs / not delivered (10)

Jira itemWhy it carried
ADS-7559 — Story — [UPG] - Adeverinte de studentPartial completion
ADS-8162 — Story — [Burse] - US5 - PlatiPartial completion
ADS-8164 — Story — [Burse] - US6 - RapoarteNot started
ADS-8177 — Story — [State de functii] - Rapoarte 20 septPartial completion
ADS-8179 — Story — [Registre Matricole] - US2 Incarcare atribute studenti pentru popularea registrelor matricolePartial completion
ADS-8599 — Story — [Asachi][BE/FE] Ajustari echivalari notePartial completion
ADS-8679 — Story — [BE/FE] Refactor studentPartial completion
ADS-8751 — Bug — [FE] Import note bulk are success dar nu importa notelePartial completion
ADS-8756 — Bug — [Asachi][BE] Stituatii din RCNot started
ADS-8763 — Task — [Asachi][BE] Import studenti pentru anul universitar 2026-2027Partial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion8Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started2Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

6 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1515 issues in the planning snapshot
Sprint review / outcome snapshot raw list2222 issues in the Friday review snapshot
Normalized sprint fact base2121 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.