Sprint Pulse

Product Pulse — University ADS Q3 W38 - 21-25 Sep

Planned sprint ADS Q3 W38 - 21-25 Sep • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 8 of 23 visible items, including 3 Stories, 1 Tasks, and 4 Bugs. Product movement was real, but the sprint was still noisy: 9 items entered after planning and 3 of them were closed. The main misses were concentrated in 15 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items23Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items8Items whose final outcome bucket is Done
Carry overs15Items not closed at sprint review
Delivered mix3 / 1 / 4Stories / Tasks / Bugs delivered
Entry kind mix14 / 9 / 0Planned / Added during sprint / Stretch visible
Readiness mix13 / 9 / 1Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended5/7Progress items were expected not to finish in this sprint

Stories done (3)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7559 — [UPG] - Adeverinte de studentPlanned
ADS-8177 — [State de functii] - Rapoarte 20 septPlanned
ADS-8179 — [Registre Matricole] - US2 Incarcare atribute studenti pentru popularea registrelor matricolePlanned

Tasks done (1)

Jira itemHow entered
ADS-8871 — [Cazari] - Import studenti Erasmus an universitar 2026-2027Added

Bugs done (4)

Jira itemHow entered
ADS-8751 — [FE] Import note bulk are success dar nu importa notelePlanned
ADS-8786 — [Asachi] - Schimbare numar credite la o disciplinaPlanned
ADS-8860 — [Prod][AWS][uni-api] Staff sync returns 500 when duplicate person mappings violate single-result contract - 2 requests/72hAdded
ADS-8896 — [Prod][AWS][uni-api] Invalid identity date poisons bulk-import Hibernate session - 12 traces/72hAdded

Carry overs / not delivered (15)

Jira itemWhy it carried
ADS-8161 — Story — [Burse] - US4 - Alocare bursePartial completion
ADS-8162 — Story — [Burse] - US5 - PlatiPartial completion
ADS-8166 — Story — [Burse] - US7 - View Student/actiuni studentPartial completion
ADS-8599 — Story — [Asachi][BE/FE] Ajustari echivalari notePartial completion
ADS-8682 — Bug — [Prod][TUIASI][Accommodations] Dependency failures cause report and list HTTP 500 burstPartial completion
ADS-8763 — Task — [Asachi][BE] Import studenti pentru anul universitar 2026-2027Dependency delay
ADS-8804 — Bug — [Asachi] - Student duplicat in catalog de restantieri la descarcareNot started
ADS-8810 — Bug — [Asachi] - Eroare alocare restantieriNot started
ADS-8812 — Story — Download RMPartial completion
ADS-8879 — Bug — [Asachi] - Eroare acces student in UMSNot started
ADS-8888 — Bug — [Cazari] - Eroare la export fisierPartial completion
ADS-8893 — Bug — [Cazari] - Corectii soldPartial completion
ADS-8897 — Bug — [Prod][TUIASI][Accommodations] Missing studentId makes accommodation create return HTTP 500Partial completion
ADS-8938 — Bug — [Asachi] - Problema echivalariNot started
ADS-8972 — Bug — [Asachi] - Problema incheiere media anuala masterNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion5Carryovers blocked by partial completion
Dependency / competing work1Delivery slipped because attention or dependency landed elsewhere
Not started3Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

5 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1414 issues in the planning snapshot
Sprint review / outcome snapshot raw list2424 issues in the Friday review snapshot
Normalized sprint fact base2323 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.