Repeated Finish promises need a different planning decision
Rolling six-month carryovers: 2026-05-14–2026-11-14. What-if: 16 finalized sprints, W30–W45.
137 of 619 Finish-planned tickets (22.1%) carried at least twice. 628/1206 eligible Finish commitments carried over (52.1%).
Team 1, Team 2, University and Mobile. Platform/Infra and Rojan-assigned work excluded. Refreshed 2026-11-22T16:52:54+02:00. Latest frozen sprint: W45.
Repeated tickets by team and category
| Team | Category | Finish-planned tickets | Repeated tickets | Repeat rate | Carryovers on repeated tickets | Longest run |
|---|---|---|---|---|---|---|
| Team 1 | Bug + Task | 204 | 47 | 23.0% | 180 | 9 |
| Team 1 | Story + Improvement | 53 | 11 | 20.8% | 39 | 6 |
| Team 2 | Bug + Task | 86 | 15 | 17.4% | 56 | 10 |
| Team 2 | Story + Improvement | 41 | 16 | 39.0% | 54 | 5 |
| University | Bug + Task | 120 | 23 | 19.2% | 72 | 7 |
| University | Story + Improvement | 39 | 14 | 35.9% | 36 | 5 |
| Mobile | Bug + Task | 44 | 2 | 4.5% | 14 | 12 |
| Mobile | Story + Improvement | 31 | 8 | 25.8% | 26 | 4 |
| Unassigned | Bug + Task | 1 | 1 | 100.0% | 6 | 6 |
| Unassigned | Story + Improvement | 0 | 0 | — | 0 | 0 |
| All teams | Bug + Task | 455 | 88 | 19.3% | 328 | 12 |
| All teams | Story + Improvement | 164 | 49 | 29.9% | 155 | 6 |
Planned-only and Overall Finish what-if, side by side
With all four types adjusted, planned-only Finish moves from 45.9% to 53.9%; Overall Finish moves from 52.9% to 61.3%. Completed counts stay fixed at 312 planned and 517 overall.
16 finalized sprints, W30–W45 · through 2026-11-14 · Platform/Rojan excluded.
Retrospective denominator simulation, not extra delivery. Planned-only measures original Finish promises. Overall includes eligible added items marked Finish at outcome. Cleanup includes still-unstarted and later-canceled items; Strict requires an observed later start. Prior parent/child activity protects commitments; the first-work calendar week remains.
Planned-only Finish
Overall Finish, including added work
Same 0–100% axes and dates. Before is brown; After what-if is teal. Percentages pool counts before dividing.
Compare all teams
| Team | Planned-only before | Planned-only after | Overall before | Overall after | Removed planned | Removed added |
|---|
Exact weekly figures for the selected team
| Sprint / planning date | Planned-only before | Planned-only after | Overall before | Overall after |
|---|
Planned vs added breakdown · all-category Cleanup
| Team | Entry | Before | Removed | After |
|---|---|---|---|---|
| Organization | Planned | 312/679 (45.9%) | 100 | 312/579 (53.9%) |
| Organization | Added | 205/299 (68.6%) | 34 | 205/265 (77.4%) |
| Team 1 | Planned | 100/240 (41.7%) | 34 | 100/206 (48.5%) |
| Team 1 | Added | 102/142 (71.8%) | 12 | 102/130 (78.5%) |
| Team 2 | Planned | 67/163 (41.1%) | 25 | 67/138 (48.6%) |
| Team 2 | Added | 39/63 (61.9%) | 10 | 39/53 (73.6%) |
| University | Planned | 99/191 (51.8%) | 26 | 99/165 (60.0%) |
| University | Added | 45/61 (73.8%) | 7 | 45/54 (83.3%) |
| Mobile | Planned | 46/86 (53.5%) | 15 | 46/71 (64.8%) |
| Mobile | Added | 19/33 (57.6%) | 5 | 19/28 (67.9%) |
Planned-only study and ticket evidence · Overall study and ticket evidence · Matched weekly CSV · Scenario totals
Share of unstarted Finish commitments
Are fewer Finish promises still unstarted by the sprint outcome? Track each team and sprint, separating planned work from added work, and Bugs/Tasks from Stories/Improvements.
Unstarted share = evidence-classified unstarted Finish commitments ÷ all original Finish commitments in that exact cohort. The denominator includes completed work and never uses the reduced what-if plan. Each chart has both issue categories. Lower suggests cleaner commitments; read it alongside Finish achievement and the counts below.
16 finalized sprints, W30–W45 · through 2026-11-14 · Platform/Rojan excluded · Same conservative work-evidence rules as the what-if.
Planned Finish commitments
Added Finish commitments
Same 0–100% axes. Bug + Task is brown; Story + Improvement is teal. Zero commitments remains missing, not 0%.
Recent planning trend
| Cohort | Previous sprints | Latest sprints | Change (lower is better) | Unknown evidence, latest |
|---|
Exact figures by sprint
| Sprint / planning date | Planned · Bug + Task | Planned · Story + Improvement | Added · Bug + Task | Added · Story + Improvement | Unknown work evidence |
|---|
Cells show unstarted / original Finish commitments (share). A commitment is counted once in its sprint and entry/category group; carrying it into another sprint is another commitment. Organization totals deduplicate within each sprint, so overlapping team attribution need not sum to Organization.
Cleanup uses the same later-started, still-unstarted and later-canceled unstarted decisions as the what-if. Strict counts only observed later starts. Prior parent/child work, time or code and the first-work calendar week remain protected. These are conservative evidence classifications, not every To Do snapshot and not proof of zero effort. Unreadable work evidence stays in the denominator, outside the unstarted count, with its unknown count shown. Added Finish intent is known at outcome. Later evidence can reclassify historical rows, particularly in Strict.
Download all teams and sprints (CSV) · Metric data (JSON) · Compare with Finish achievement
Small changes to try over the next four sprints
Among repeated tickets, 272/483 carryovers (56.3%) ended To Do; 89 ended in testing or review. Status is a point-in-time proxy for work, not effort measurement.
| Observed pattern | Small process change to try | Check after four sprints |
|---|---|---|
| Finish promises remain To Do | Name a protected delivery slot and accountable owner before renewing Finish. | Share ending To Do; count of third consecutive misses. |
| Review/testing work carries over | Reserve reviewer and tester capacity; agree the completion endpoint. | Age and volume of review/testing carryovers. |
| Repeated promises recycle | After two misses, explicitly split, defer, or protect capacity. | Carryover age distribution and six-plus misses. |
| Prerequisites remain unresolved | Confirm required inputs and a credible dependency date at planning. | Carryovers with a prerequisite already missing at planning. |
Repeated tickets in the selected period
Grouped by team, then Bug + Task and Story + Improvement. Six-month tickets CSV · Six-month statistics CSV
No repeated Finish promises match this period and search.
Team 1 · Bug + Task
| Ticket and evidence | Type | Monday | Finish carryovers | Longest run | Planning appearances | Original stack effort | Current status |
|---|---|---|---|---|---|---|---|
ADS-8209 · [Prod][AWS][legacy-web] GET /api/v2/fisiere/view returns HTTP 500 when M_fisiere.php calls query() on nullSprint evidenceADS Q3 W28 - 13-17 Jul · To Do · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · To Do · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · To Do · finalized_registry ADS Q3 W31 - 03-07 Aug · To Do · finalized_registry ADS Q3 W32 - 10-14 Aug · To Do · finalized_registry ADS Q3 W33 - 17-21 Aug · To Do · finalized_registry ADS Q3 W34 - 24-28 Aug · To Do · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · To Do · finalized_registry ADS Q3 W36 - 07-11 Sep · To Do · finalized_registry | Bug | Jira | 9 | 9 | 9 | Original not recorded | In Progress |
ADS-7389 · AdservioAPI.php: svcAuth self-call failures turn web API endpoints into HTTP 500 - 20 hits/FridaySprint evidenceADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction | Bug | Jira | 8 | 8 | 8 | Original not recorded | To Do |
ADS-6712 · [Note/absențe] - Recuperare informațiiSprint evidenceADS Q2 W19 - 11-15 May · To Do · jira_history_reconstruction ADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction | Task | Jira | 7 | 7 | 9 | Original not recorded | Canceled |
ADS-7390 · rooms-api: room search endpoint returns HTTP 500 - 3 hits/FridaySprint evidenceADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction | Bug | Jira | 7 | 7 | 7 | Original not recorded | To Do |
ADS-4439 · [Teste si chestionare] - Numarul de destinatari care se afiseaza nu corespunde cu numarul real de destinatariSprint evidenceADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction | Bug | Jira | 6 | 6 | 6 | Original not recorded | To Do |
ADS-6698 · [FE/BE] Restrictie vizualizare fise scolareSprint evidenceADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction | Bug | Jira | 6 | 6 | 6 | Original not recorded | To Do |
ADS-7575 · M_export.php / Export.php: student export references missing second-semester average column and returns HTTP 500 on /ro/secretary/export/elevi - 16 hits/24hSprint evidenceADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · In Progress · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · In Progress · jira_history_reconstruction | Bug | Jira | 6 | 6 | 7 | Original not recorded | To Do |
ADS-7803 · [FE/BE/MOB/UNI] - TitulaturaSprint evidenceADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q4 W40 - 05-09 Oct · Ready for testing · finalized_registry ADS Q4 W41 - 12-16 Oct · Ready for testing · finalized_registry ADS Q4 W42 - 19-23 Oct · Ready for testing · finalized_registry | Task | Task reference | 6 | 3 | 11 | Original not recorded | Merged |
ADS-7852 · [BE]: Dezactivare actiuni noteaza (si bulk) daca media anuala si/sau media semestriala este incheiataSprint evidenceADS Q2 W24 - 15-19 Jun · In Progress · jira_history_reconstruction ADS Q3 W33 - 17-21 Aug · Ready to merge · finalized_registry ADS Q3 W34 - 24-28 Aug · Ready to merge · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · Ready to merge · finalized_registry ADS Q3 W36 - 07-11 Sep · To Do · finalized_registry ADS Q3 W37 - 14-18 Sep · Ready for testing · finalized_registry | Task | Jira | 6 | 5 | 10 | Original not recorded | Done |
ADS-8366 · [Prod][AWS][legacy-web] Tenantless API requests hit null school DB handle across timetable, grades, and portfolioSprint evidenceADS Q3 W31 - 03-07 Aug · In Progress · finalized_registry ADS Q3 W32 - 10-14 Aug · To Do · finalized_registry ADS Q3 W33 - 17-21 Aug · To Do · finalized_registry ADS Q3 W34 - 24-28 Aug · To Do · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · To Do · finalized_registry ADS Q3 W36 - 07-11 Sep · To Do · finalized_registry | Bug | Jira | 6 | 6 | 6 | Original not recorded | To Do |
ADS-5919 · [Fotografii] - Distribuirea nu este afișată exclusiv pe clasele sau grupele configurate în modulul ClaseSprint evidenceADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction | Bug | Jira | 5 | 5 | 6 | Original not recorded | Canceled |
ADS-7448 · [BE] Grades.php: deleting a grade can deadlock on cat_note and return HTTP 500 - 8 hits/24hSprint evidenceADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction | Bug | Jira | 5 | 5 | 7 | Original not recorded | Done |
ADS-8580 · Recuperare date sterse elev ID [redacted]Sprint evidenceADS Q3 W35 - 31 Aug-04 Sep · In Progress · finalized_registry ADS Q3 W36 - 07-11 Sep · In Progress · finalized_registry ADS Q3 W37 - 14-18 Sep · In Progress · finalized_registry ADS Q3 W38 - 21-25 Sep · In Progress · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · In Progress · finalized_registry | Task | Jira | 5 | 5 | 7 | Original not recorded | Canceled |
ADS-8598 · [BE] aflare cine l-a sters pe elev ID [redacted]Sprint evidenceADS Q3 W35 - 31 Aug-04 Sep · In Progress · finalized_registry ADS Q3 W36 - 07-11 Sep · In Progress · finalized_registry ADS Q3 W37 - 14-18 Sep · In Progress · finalized_registry ADS Q3 W38 - 21-25 Sep · In Progress · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · In Progress · finalized_registry | Task | Jira | 5 | 5 | 7 | Original not recorded | Canceled |
ADS-406 · [Files] Missing description in ‘’Istoric’ when sharing documentsSprint evidenceADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · In Progress · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction | Bug | Jira | 4 | 4 | 5 | Original not recorded | Done |
ADS-5722 · [BE/FE] Modal adauga noteSprint evidenceADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · In Progress · jira_history_reconstruction | Bug | Jira | 4 | 4 | 7 | Original not recorded | Done |
ADS-7009 · Dezactivare actiuni noteaza(si bulk) daca media anuala si/sau media semestriala este incheiataSprint evidenceADS Q2 W19 - 11-15 May · To Do · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · Testing · jira_history_reconstruction | Task | Jira | 4 | 3 | 5 | Original not recorded | Done |
ADS-7451 · [BE] - Condica - Activitati duplicateSprint evidenceADS Q2 W19 - 11-15 May · To Do · jira_history_reconstruction ADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · In Progress · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · In Progress · jira_history_reconstruction | Bug | Jira | 4 | 4 | 5 | Original not recorded | Done |
ADS-7653 · Clase_profesori.php / M_cmc.php: teacher-class assignment insert fails FK constraint in cat_cadre2materii2clase - 2 errors/24hSprint evidenceADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction | Bug | Jira | 4 | 4 | 5 | Original not recorded | Canceled |
ADS-7654 · AverageCalculator: writes succeed while class-average recomputation fails when class formula is missingSprint evidenceADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q3 W33 - 17-21 Aug · To Do · finalized_registry | Bug | Jira | 4 | 3 | 7 | Original not recorded | To Do |
ADS-8260 · [Prod][AWS][Web] Global-message modal fails on missing CMC metadata, including teacher-tab HTTP 500Sprint evidenceADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry ADS Q4 W40 - 05-09 Oct · To Do · finalized_registry ADS Q4 W41 - 12-16 Oct · To Do · finalized_registry ADS Q4 W42 - 19-23 Oct · To Do · finalized_registry | Bug | Jira | 4 | 4 | 4 | Original not recorded | To Do |
ADS-8506 · [Prod][AWS][legacy-web] Student export binds an empty DATE value and silently returns no rows - 10 errors/72hSprint evidenceADS Q3 W33 - 17-21 Aug · To Do · finalized_registry ADS Q3 W34 - 24-28 Aug · To Do · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · To Do · finalized_registry ADS Q3 W36 - 07-11 Sep · To Do · finalized_registry | Bug | Jira | 4 | 4 | 4 | Original not recorded | Done |
ADS-4857 · [Mesagerie] - Restricționarea mesajelor de grup, conform configurărilor setateSprint evidenceADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction | Bug | Jira | 3 | 3 | 5 | Original not recorded | Canceled |
ADS-7533 · medii_generale.php: secretary final averages page reads missing $cicluSelectatID when cycle filter is empty - 3 warnings/24hSprint evidenceADS Q2 W19 - 11-15 May · To Do · jira_history_reconstruction ADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction | Bug | Jira | 3 | 3 | 4 | Original not recorded | Done |
ADS-7618 · [BE/FE] Chestionare - Descarcarea raspunsurilor individuale descarca mereu primul parinte din lista, iar status completare este gresitSprint evidenceADS Q2 W21 - 25-29 Mai · In Progress · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · In Progress · jira_history_reconstruction ADS Q2 W23 - 08-12 June · In Progress · jira_history_reconstruction | Bug | Jira | 3 | 3 | 4 | Original not recorded | Done |
ADS-7907 · [BE] Refactoring SQL_CALC_FOUND_ROWSSprint evidenceADS Q3 W28 - 13-17 Jul · In Progress · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · In Progress · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · In Progress · finalized_registry | Task | Jira | 3 | 3 | 7 | Original not recorded | Done |
ADS-7908 · [Prod][AWS][legacy-web] Auth recaptcha helper dereferences null verification responseSprint evidenceADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction | Bug | Jira | 3 | 3 | 3 | Original not recorded | To Do |
ADS-8510 · [FE] diferenta numar elevi in raportul "promovabilitae elevi"Sprint evidenceADS Q3 W34 - 24-28 Aug · To Do · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · To Do · finalized_registry ADS Q3 W36 - 07-11 Sep · To Do · finalized_registry | Bug | Jira | 3 | 3 | 4 | Original not recorded | Done |
ADS-8569 · [BE] transfer date comasare scoliSprint evidenceADS Q3 W35 - 31 Aug-04 Sep · In Progress · finalized_registry ADS Q3 W36 - 07-11 Sep · To Do · finalized_registry ADS Q3 W37 - 14-18 Sep · Code Review · finalized_registry | Task | Jira | 3 | 3 | 4 | Original not recorded | Done |
ADS-8570 · [FE] inactivare conturi in urma comasariiSprint evidenceADS Q3 W35 - 31 Aug-04 Sep · To Do · finalized_registry ADS Q3 W36 - 07-11 Sep · To Do · finalized_registry ADS Q3 W37 - 14-18 Sep · Code Review · finalized_registry | Task | Jira | 3 | 3 | 4 | Original not recorded | Done |
ADS-8760 · [FE]: Schimbari pe Suprascrieri si transferuriSprint evidenceADS Q3 W37 - 14-18 Sep · To Do · finalized_registry ADS Q3 W38 - 21-25 Sep · To Do · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry | Task | Jira | 3 | 3 | 3 | Original not recorded | Merged |
ADS-9047 · Adaugare coordonator clasa in lista de destinatari propusiSprint evidenceADS Q4 W41 - 12-16 Oct · Ready for testing · finalized_registry ADS Q4 W42 - 19-23 Oct · Code Review · finalized_registry ADS Q4 W43 - 26-30 Oct · Code Review · finalized_registry | Task | Jira | 3 | 3 | 5 | Original not recorded | Done |
ADS-9239 · [Superset] Raport orar pe scoala Sprint evidenceADS Q4 W42 - 19-23 Oct · To Do · finalized_registry ADS Q4 W43 - 26-30 Oct · To Do · finalized_registry ADS Q4 W44 - 02-06 Nov · To Do · finalized_registry | Task | Jira | 3 | 3 | 4 | Original not recorded | In Progress |
ADS-3896 · [Classes][Homework] -Problema la Trimiterea Temelor Corectate din aplicatia de mobil Sprint evidenceADS Q3 W28 - 13-17 Jul · To Do · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · To Do · jira_history_reconstruction | Bug | Jira | 2 | 2 | 2 | Original not recorded | To Do |
ADS-6899 · [Medii] Calcul gresit medie semestreSprint evidenceADS Q2 W19 - 11-15 May · To Do · jira_history_reconstruction ADS Q2 W20 - 18-22 May · In Progress · jira_history_reconstruction | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-7460 · Absences time interval export_xls returns HTTP 500 for inverted date range (6 errors/24h)Sprint evidenceADS Q2 W20 - 18-22 May · In Progress · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction | Bug | Jira | 2 | 1 | 4 | Original not recorded | Done |
ADS-7732 · TUIASI M_fisiere.php: file list query expects fsScimCeacSyncFsID missing from on-prem schema and breaks document listings - 12 errors/24hSprint evidenceADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-8061 · [Prod][AWS][legacy-web] School-transfer edit recalculates status for NULL student ID - 64 errors/72hSprint evidenceADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction | Bug | Jira | 2 | 2 | 2 | Original not recorded | To Do |
ADS-8062 · [Prod][AWS][legacy-web] Certificate template fetch returns 500 when forms schema lookup gets 403 - 26 errors/72hSprint evidenceADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction | Bug | Jira | 2 | 2 | 2 | Original not recorded | To Do |
ADS-8455 · [AWS prod][Teacher school years] M_cadre omits pagination total after merge - 396 errors/6hSprint evidenceADS Q3 W32 - 10-14 Aug · To Do · finalized_registry ADS Q3 W33 - 17-21 Aug · To Do · finalized_registry | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-8841 · [FE] Clase lipsa din statisticile de promovabilitate pentru anul scolar 2025-2026Sprint evidenceADS Q3 W38 - 21-25 Sep · To Do · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · Testing · finalized_registry | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-8953 · [BE] statistici- valorile pentru mediul de provenienta sunt afisate gresit pentru anul scolar anteriorSprint evidenceADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry ADS Q4 W40 - 05-09 Oct · Testing · finalized_registry | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-9095 · [FE]: Fix erori din consolaSprint evidenceADS Q4 W40 - 05-09 Oct · To Do · finalized_registry ADS Q4 W41 - 12-16 Oct · To Do · finalized_registry | Task | Jira | 2 | 2 | 3 | Original not recorded | Canceled |
ADS-9167 · [BE]: Reset activation code timer after email/phone changeSprint evidenceADS Q4 W41 - 12-16 Oct · Ready for testing · finalized_registry ADS Q4 W42 - 19-23 Oct · Ready for testing · finalized_registry | Task | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-9297 · [FE] calcul medie purtare -nu e setata by default purtare standard romaniaSprint evidenceADS Q4 W43 - 26-30 Oct · To Do · finalized_registry ADS Q4 W44 - 02-06 Nov · Testing · finalized_registry | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-9392 · [Prod][Notifications] notifications-event-manager crashes overnight on "MySQL server has gone away": tenant DB connection is reused past wait_timeoutSprint evidenceADS Q4 W44 - 02-06 Nov · In Progress · finalized_registry ADS Q4 W45 - 09-13 Nov · In Progress · finalized_registry | Bug | Jira | 2 | 2 | 2 | Original not recorded | In Progress |
ADS-9415 · [BE] Import SIIIR - Nomenclator nou & specializareSprint evidenceADS Q4 W44 - 02-06 Nov · In Progress · finalized_registry ADS Q4 W45 - 09-13 Nov · In Progress · finalized_registry | Task | Jira | 2 | 2 | 2 | Original not recorded | To Do |
Team 1 · Story + Improvement
| Ticket and evidence | Type | Monday | Finish carryovers | Longest run | Planning appearances | Original stack effort | Current status |
|---|---|---|---|---|---|---|---|
ADS-6545 · [SDK] Implementare v1 layer comunicare native-web *post message bridgeSprint evidenceADS Q2 W20 - 18-22 May · In Progress · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · Ready to merge · jira_history_reconstruction | Story | Not matched | 6 | 5 | 8 | Original not recorded | Done |
ADS-9068 · Move fs events to object + previous_values; stop signalling moves via a `moved` field on createdSprint evidenceADS Q4 W40 - 05-09 Oct · To Do · finalized_registry ADS Q4 W41 - 12-16 Oct · To Do · finalized_registry ADS Q4 W42 - 19-23 Oct · To Do · finalized_registry ADS Q4 W43 - 26-30 Oct · To Do · finalized_registry ADS Q4 W44 - 02-06 Nov · To Do · finalized_registry ADS Q4 W45 - 09-13 Nov · To Do · finalized_registry | Improvement | Not matched | 6 | 6 | 6 | Original not recorded | To Do |
ADS-7817 · [SIIIR] - Import cadre didacticeSprint evidenceADS Q3 W37 - 14-18 Sep · In Progress · finalized_registry ADS Q3 W38 - 21-25 Sep · In Progress · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · In Progress · finalized_registry ADS Q4 W40 - 05-09 Oct · In Progress · finalized_registry ADS Q4 W41 - 12-16 Oct · In Progress · finalized_registry | Story | Monday | 5 | 5 | 6 | BE L (10d); FE M (5d) Current: BE L, FE M | Done |
ADS-7816 · [SIIIR] - Import claseSprint evidenceADS Q3 W31 - 03-07 Aug · In Progress · finalized_registry ADS Q3 W32 - 10-14 Aug · In Progress · finalized_registry ADS Q3 W33 - 17-21 Aug · In Progress · finalized_registry ADS Q3 W34 - 24-28 Aug · In Progress · finalized_registry | Story | Monday | 4 | 4 | 8 | BE M (5d); FE M (5d) Current: BE M, FE M | Done |
ADS-8567 · NOMENCLATOR - Refactor structura clasaSprint evidenceADS Q4 W40 - 05-09 Oct · In Progress · finalized_registry ADS Q4 W41 - 12-16 Oct · In Progress · finalized_registry ADS Q4 W42 - 19-23 Oct · In Progress · finalized_registry ADS Q4 W43 - 26-30 Oct · Testing · finalized_registry | Story | Monday | 4 | 4 | 7 | BE M (5d); FE S (2d); Mob S (2d) Current: BE M, FE M, Mob S | Done |
ADS-6499 · Implementat CRUD Etnii in LaravelSprint evidenceADS Q2 W19 - 11-15 May · To Do · jira_history_reconstruction ADS Q2 W20 - 18-22 May · In Progress · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · Ready for testing · jira_history_reconstruction | Story | Not matched | 3 | 3 | 4 | Original not recorded | Done |
ADS-6725 · Update Adeverinta de elevSprint evidenceADS Q4 W43 - 26-30 Oct · To Do · finalized_registry ADS Q4 W44 - 02-06 Nov · To Do · finalized_registry ADS Q4 W45 - 09-13 Nov · To Do · finalized_registry | Improvement | Not matched | 3 | 3 | 3 | Original not recorded | Merged |
ADS-6360 · [Catalog PDF] - Număr indicatori incorect – SemestreSprint evidenceADS Q2 W20 - 18-22 May · In Progress · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · Ready for testing · jira_history_reconstruction | Story | Not matched | 2 | 2 | 5 | Original not recorded | Done |
ADS-8004 · [FE] - Elevii transferati apar in statistici ca "medii neconfirmate"Sprint evidenceADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction | Improvement | Not matched | 2 | 2 | 2 | Original not recorded | To Do |
ADS-8105 · Impartirea pe moduleSprint evidenceADS Q3 W29 - 20-24 Jul · In Progress · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · In Progress · finalized_registry | Story | Monday | 2 | 2 | 5 | BE L (10d); FE L (10d); Mob S (2d) Current: BE L, FE L, Mob M | Done |
ADS-8723 · Posibilitate generare orar atunci cand exista 2 profesori principaliSprint evidenceADS Q3 W37 - 14-18 Sep · Testing · finalized_registry ADS Q3 W38 - 21-25 Sep · Testing · finalized_registry | Improvement | Not matched | 2 | 2 | 3 | Original not recorded | Done |
Team 2 · Bug + Task
| Ticket and evidence | Type | Monday | Finish carryovers | Longest run | Planning appearances | Original stack effort | Current status |
|---|---|---|---|---|---|---|---|
ADS-2590 · [Students] - Trebuie inlocuit articolul de la model import automat-date de completare si sa se deschida articolul din manualul de utilizare daca de da click pe linkul respectiv Sprint evidenceADS Q3 W28 - 13-17 Jul · In Progress · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · In Progress · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · To Do · finalized_registry ADS Q3 W31 - 03-07 Aug · To Do · finalized_registry ADS Q3 W32 - 10-14 Aug · To Do · finalized_registry ADS Q3 W33 - 17-21 Aug · To Do · finalized_registry ADS Q3 W34 - 24-28 Aug · To Do · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · To Do · finalized_registry ADS Q3 W36 - 07-11 Sep · To Do · finalized_registry ADS Q3 W37 - 14-18 Sep · To Do · finalized_registry | Bug | Jira | 10 | 10 | 11 | Original not recorded | Done |
ADS-7519 · [BE] "Afișează noutăți Adservio" toggle is non-functionalSprint evidenceADS Q2 W19 - 11-15 May · To Do · jira_history_reconstruction ADS Q2 W20 - 18-22 May · In Progress · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · In Progress · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · In Progress · jira_history_reconstruction ADS Q2 W23 - 08-12 June · In Progress · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · Code Review · jira_history_reconstruction | Task | Jira | 6 | 6 | 7 | Original not recorded | Done |
ADS-7279 · [Billing] - Implementare Stripe + Apple pay + Google paySprint evidenceADS Q3 W33 - 17-21 Aug · Ready for testing · finalized_registry ADS Q3 W34 - 24-28 Aug · In Progress · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · In Progress · finalized_registry ADS Q3 W36 - 07-11 Sep · Ready for testing · finalized_registry ADS Q3 W37 - 14-18 Sep · Testing · finalized_registry | Task | Task reference | 5 | 5 | 6 | Node M (5d) Current: Node M | Done |
ADS-8501 · S3: Ștergere variabile OSS vechi și verificat că totul merge bineSprint evidenceADS Q3 W33 - 17-21 Aug · To Do · finalized_registry ADS Q3 W34 - 24-28 Aug · To Do · finalized_registry ADS Q3 W37 - 14-18 Sep · In Progress · finalized_registry ADS Q3 W38 - 21-25 Sep · Code Review · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · In Progress · finalized_registry | Task | Jira | 5 | 3 | 6 | Original not recorded | Done |
ADS-8733 · [Prod][Billing] - Refactor charges cronSprint evidenceADS Q3 W37 - 14-18 Sep · To Do · finalized_registry ADS Q3 W38 - 21-25 Sep · To Do · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry ADS Q4 W40 - 05-09 Oct · To Do · finalized_registry ADS Q4 W41 - 12-16 Oct · To Do · finalized_registry | Bug | Jira | 5 | 5 | 5 | Original not recorded | To Do |
ADS-9019 · stergere "servicii asignate" ID [redacted]Sprint evidenceADS Q4 W40 - 05-09 Oct · To Do · finalized_registry ADS Q4 W41 - 12-16 Oct · To Do · finalized_registry ADS Q4 W42 - 19-23 Oct · To Do · finalized_registry ADS Q4 W43 - 26-30 Oct · To Do · finalized_registry ADS Q4 W44 - 02-06 Nov · In Progress · finalized_registry | Task | Jira | 5 | 5 | 6 | Original not recorded | Done |
ADS-7191 · [BE] - Tabela subscription_organizations/subscription_users se populeaza chiar daca BE intoarce mesaj de eroare la assignSprint evidenceADS Q2 W19 - 11-15 May · To Do · jira_history_reconstruction ADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction | Task | Jira | 3 | 3 | 4 | Original not recorded | Canceled |
ADS-7421 · [BE] Cleanup NoutatiSprint evidenceADS Q3 W36 - 07-11 Sep · To Do · finalized_registry ADS Q3 W37 - 14-18 Sep · To Do · finalized_registry ADS Q3 W38 - 21-25 Sep · In Progress · finalized_registry | Task | Jira | 3 | 3 | 4 | Original not recorded | Done |
ADS-4007 · [BE][Subscriptions] - Comportament ciudat featureflags in cazul in care sunt dezactivate subscriptiileSprint evidenceADS Q3 W28 - 13-17 Jul · To Do · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · To Do · jira_history_reconstruction | Bug | Jira | 2 | 2 | 2 | Original not recorded | In Progress |
ADS-7272 · M_user_api.php / M_user.php: subscriptions features lookup fails hard when subscriptions-api-svc is slow or down - 20 errors/48hSprint evidenceADS Q3 W36 - 07-11 Sep · To Do · finalized_registry ADS Q3 W37 - 14-18 Sep · To Do · finalized_registry | Bug | Jira | 2 | 2 | 4 | Original not recorded | Canceled |
ADS-7343 · [Stiri] - Distribuie UpdatesSprint evidenceADS Q2 W19 - 11-15 May · In Progress · jira_history_reconstruction ADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction | Task | Task reference | 2 | 2 | 4 | Node M (5d) Current: Node M | Done |
ADS-7419 · [SUBSCRIPTIONS] - Bug-uriSprint evidenceADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · Ready for testing · jira_history_reconstruction | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-7537 · HTTP 500 on POST /api/v2/billing/invoices when invoice series lookup returns multiple rowsSprint evidenceADS Q2 W19 - 11-15 May · To Do · jira_history_reconstruction ADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction | Bug | Jira | 2 | 2 | 3 | Original not recorded | Canceled |
ADS-8798 · [MOB][FE] - Local front-end proxy for mobile appSprint evidenceADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry ADS Q4 W40 - 05-09 Oct · In Progress · finalized_registry | Task | Jira | 2 | 2 | 4 | Original not recorded | Done |
ADS-9210 · Migrare Timezone GMT+3 -> UTC Sprint evidenceADS Q4 W42 - 19-23 Oct · In Progress · finalized_registry ADS Q4 W43 - 26-30 Oct · In Progress · finalized_registry | Task | Jira | 2 | 2 | 4 | Original not recorded | Testing |
Team 2 · Story + Improvement
| Ticket and evidence | Type | Monday | Finish carryovers | Longest run | Planning appearances | Original stack effort | Current status |
|---|---|---|---|---|---|---|---|
ADS-6159 · Notification Center for MobileSprint evidenceADS Q3 W32 - 10-14 Aug · In Progress · finalized_registry ADS Q3 W36 - 07-11 Sep · In Progress · finalized_registry ADS Q3 W37 - 14-18 Sep · In Progress · finalized_registry ADS Q3 W38 - 21-25 Sep · In Progress · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · In Progress · finalized_registry | Story | Monday | 5 | 4 | 12 | Node M (5d); Mob L (10d) Current: Node M, Mob M | Done |
ADS-6494 · Log levels & Log formatsSprint evidenceADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · In Progress · jira_history_reconstruction ADS Q2 W23 - 08-12 June · Code Review · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · Code Review · jira_history_reconstruction | Story | Not matched | 5 | 5 | 6 | Original not recorded | Done |
ADS-7354 · [Abonamente] - Gestionare recurență pachete anualeSprint evidenceADS Q3 W38 - 21-25 Sep · In Progress · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · In Progress · finalized_registry ADS Q4 W40 - 05-09 Oct · In Progress · finalized_registry ADS Q4 W41 - 12-16 Oct · Ready for testing · finalized_registry ADS Q4 W42 - 19-23 Oct · In Progress · finalized_registry | Story | Not matched | 5 | 5 | 10 | Original not recorded | Done |
ADS-1757 · [Financiar] - Plati partialeSprint evidenceADS Q2 W20 - 18-22 May · Code Review · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · Code Review · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · In Progress · jira_history_reconstruction ADS Q2 W23 - 08-12 June · In Progress · jira_history_reconstruction | Story | Not matched | 4 | 4 | 6 | Original not recorded | Done |
ADS-6675 · [Financiar] - Managementul penalitatilorSprint evidenceADS Q3 W27 - 06-10 Jul · In Progress · jira_history_reconstruction ADS Q3 W28 - 13-17 Jul · In Progress · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · Ready for testing · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · Testing · finalized_registry | Story | Monday | 4 | 4 | 6 | FE S (2d); Node M (5d) Current: Node L | Done |
ADS-7405 · [BE] - Local CacheSprint evidenceADS Q2 W20 - 18-22 May · In Progress · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · In Progress · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · In Progress · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · Code Review · jira_history_reconstruction | Story | Not matched | 4 | 3 | 6 | Original not recorded | Done |
ADS-7430 · [Admitere v2][Taxe] - 5. Export platile candidatului&extinderea cu alte informatii ale candidatilorSprint evidenceADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction | Story | Not matched | 4 | 4 | 5 | Original not recorded | Done |
ADS-1321 · [BE][LCY][FE] - Adding to the student edit several mother tonguesSprint evidenceADS Q4 W43 - 26-30 Oct · To Do · finalized_registry ADS Q4 W44 - 02-06 Nov · To Do · finalized_registry ADS Q4 W45 - 09-13 Nov · In Progress · finalized_registry | Story | Monday | 3 | 3 | 3 | Original not recorded | Merged |
ADS-7849 · Stergere date S3Sprint evidenceADS Q3 W33 - 17-21 Aug · To Do · finalized_registry ADS Q3 W34 - 24-28 Aug · To Do · finalized_registry ADS Q4 W41 - 12-16 Oct · To Do · finalized_registry | Story | Monday | 3 | 2 | 8 | BE S (2d) Current: BE M | To Do |
ADS-8259 · [Abonamente][RC] - Rambursare clientiSprint evidenceADS Q3 W35 - 31 Aug-04 Sep · To Do · finalized_registry ADS Q3 W38 - 21-25 Sep · To Do · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry | Story | Monday | 3 | 2 | 6 | Original not recorded | Done |
ADS-8343 · IntegrationSprint evidenceADS Q3 W35 - 31 Aug-04 Sep · In Progress · finalized_registry ADS Q3 W36 - 07-11 Sep · In Progress · finalized_registry ADS Q3 W37 - 14-18 Sep · Code Review · finalized_registry | Story | Not matched | 3 | 3 | 4 | Original not recorded | Done |
ADS-8383 · [BE] - Local Cache BillingSprint evidenceADS Q3 W33 - 17-21 Aug · In Progress · finalized_registry ADS Q3 W34 - 24-28 Aug · In Progress · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · Ready for testing · finalized_registry | Story | Not matched | 3 | 3 | 6 | Original not recorded | Done |
ADS-4026 · [Abonamente][Admin] - Option to disable packagesSprint evidenceADS Q3 W35 - 31 Aug-04 Sep · In Progress · finalized_registry ADS Q3 W36 - 07-11 Sep · Code Review · finalized_registry | Improvement | Not matched | 2 | 2 | 3 | Original not recorded | Done |
ADS-7251 · Mutarea subscriptii de pe recurenta An scolar pe recurenta an calendaristicSprint evidenceADS Q3 W33 - 17-21 Aug · Testing · finalized_registry ADS Q3 W34 - 24-28 Aug · Ready to merge · finalized_registry | Story | Monday | 2 | 2 | 4 | Node L (10d) Current: Node L | Done |
ADS-8671 · [AI - MCP] Teacher summariesSprint evidenceADS Q3 W38 - 21-25 Sep · In Progress · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · In Progress · finalized_registry | Story | Not matched | 2 | 2 | 5 | Original not recorded | Done |
ADS-8769 · [Abonamente][Admin][Statistici] - UpdatesSprint evidenceADS Q3 W38 - 21-25 Sep · To Do · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry | Improvement | Not matched | 2 | 2 | 4 | Original not recorded | Done |
University · Bug + Task
| Ticket and evidence | Type | Monday | Finish carryovers | Longest run | Planning appearances | Original stack effort | Current status |
|---|---|---|---|---|---|---|---|
ADS-6438 · [BE][UNI] - Sincronizare ID-uri Ani universitari/scolari - UNI/preuni - masterSprint evidenceADS Q3 W27 - 06-10 Jul · Ready to merge · jira_history_reconstruction ADS Q3 W28 - 13-17 Jul · Ready to merge · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · Ready to merge · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · Ready to merge · finalized_registry ADS Q3 W31 - 03-07 Aug · Ready to merge · finalized_registry ADS Q3 W32 - 10-14 Aug · Ready to merge · finalized_registry ADS Q3 W33 - 17-21 Aug · Ready to merge · finalized_registry | Task | Jira | 7 | 7 | 10 | Original not recorded | Done |
ADS-7666 · accommodations-api: shared HTTP 500 burst on POST /api/v2/accommodations/dorms/list and related endpoints - 16 hits/20mSprint evidenceADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · In Progress · jira_history_reconstruction ADS Q3 W28 - 13-17 Jul · In Progress · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · To Do · jira_history_reconstruction | Bug | Jira | 7 | 7 | 10 | Original not recorded | Done |
ADS-8326 · [BE-PHP][Cazari] - La decazare soldurie apar incorect fata de fisa studentilorSprint evidenceADS Q3 W30 - 27-31 Jul · To Do · finalized_registry ADS Q3 W33 - 17-21 Aug · To Do · finalized_registry ADS Q3 W34 - 24-28 Aug · Testing · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · Testing · finalized_registry ADS Q3 W36 - 07-11 Sep · Testing · finalized_registry | Bug | Jira | 5 | 4 | 10 | Original not recorded | Canceled |
ADS-8866 · [Asachi] - Problema echivalariSprint evidenceADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry ADS Q4 W40 - 05-09 Oct · To Do · finalized_registry ADS Q4 W41 - 12-16 Oct · To Do · finalized_registry ADS Q4 W42 - 19-23 Oct · To Do · finalized_registry | Bug | Jira | 4 | 4 | 5 | Original not recorded | Done |
ADS-8938 · [Asachi] - Problema echivalariSprint evidenceADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry ADS Q4 W40 - 05-09 Oct · To Do · finalized_registry ADS Q4 W41 - 12-16 Oct · To Do · finalized_registry ADS Q4 W42 - 19-23 Oct · To Do · finalized_registry | Bug | Jira | 4 | 4 | 5 | Original not recorded | Canceled |
ADS-9259 · Download RM cu Observatii si SemnatariSprint evidenceADS Q4 W42 - 19-23 Oct · In Progress · finalized_registry ADS Q4 W43 - 26-30 Oct · In Progress · finalized_registry ADS Q4 W44 - 02-06 Nov · In Progress · finalized_registry ADS Q4 W45 - 09-13 Nov · Ready to merge · finalized_registry | Task | Jira | 4 | 4 | 4 | Original not recorded | In Progress |
ADS-7388 · docgen2-api: gradebook view/download endpoints return HTTP 500 - 15 hits/FridaySprint evidenceADS Q2 W20 - 18-22 May · To Do · jira_history_reconstruction ADS Q2 W21 - 25-29 Mai · To Do · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction | Bug | Jira | 3 | 3 | 4 | Original not recorded | To Do |
ADS-7688 · [BE] [Studenti] [Muzica]- Studentul nu este unificat pe baza CNP-ului la importSprint evidenceADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction | Bug | Jira | 3 | 3 | 4 | Original not recorded | Done |
ADS-8147 · [BE] - Nu apar studentii pe sesiunea 2Sprint evidenceADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction ADS Q3 W28 - 13-17 Jul · To Do · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · To Do · jira_history_reconstruction | Bug | Jira | 3 | 3 | 4 | Original not recorded | Done |
ADS-8804 · [Asachi] - Student duplicat in catalog de restantieri la descarcareSprint evidenceADS Q3 W38 - 21-25 Sep · To Do · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry ADS Q4 W40 - 05-09 Oct · To Do · finalized_registry | Bug | Jira | 3 | 3 | 4 | Original not recorded | Done |
ADS-8810 · [Asachi] - Eroare alocare restantieriSprint evidenceADS Q3 W38 - 21-25 Sep · To Do · finalized_registry ADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry ADS Q4 W40 - 05-09 Oct · In Progress · finalized_registry | Bug | Jira | 3 | 3 | 4 | Original not recorded | Done |
ADS-8972 · [Asachi] - Problema incheiere media anuala masterSprint evidenceADS Q3 W39 - 28 Sep-02 Oct · Ready for testing · finalized_registry ADS Q4 W41 - 12-16 Oct · Ready for testing · finalized_registry ADS Q4 W42 - 19-23 Oct · To Do · finalized_registry | Bug | Jira | 3 | 2 | 5 | Original not recorded | Done |
ADS-8981 · Sterge permisiunile vechi - scholarship allocation Sprint evidenceADS Q3 W39 - 28 Sep-02 Oct · To Do · finalized_registry ADS Q4 W41 - 12-16 Oct · In Progress · finalized_registry ADS Q4 W42 - 19-23 Oct · In Progress · finalized_registry | Task | Jira | 3 | 2 | 4 | Original not recorded | Done |
ADS-7708 · [BE] - Personal universitar: Numele nu se actualizeaza corect dupa editareSprint evidenceADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · In Progress · jira_history_reconstruction | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-7880 · TUIASI uni-api: catalog import and adjacent grades endpoints return HTTP 500 - 23 hits/72hSprint evidenceADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · In Progress · jira_history_reconstruction | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-8111 · [FE/BE] - In centralizator note nu apare numele unei disciplineSprint evidenceADS Q3 W27 - 06-10 Jul · In Progress · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · To Do · jira_history_reconstruction | Bug | Jira | 2 | 1 | 4 | Original not recorded | Done |
ADS-8118 · [BE] - Lipsa nota si catalog deschis pe restantieriSprint evidenceADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction ADS Q3 W28 - 13-17 Jul · To Do · jira_history_reconstruction | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-8534 · Asachi - Nu afiseaza an de studiu pentru studentii din anul 1 (2025-2026)din situatie scolaraSprint evidenceADS Q3 W34 - 24-28 Aug · Ready to merge · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · In Progress · finalized_registry | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-8593 · [Prod][TUIASI][legacy-web] Admin edit reads missing suppressAdminEvent flag - 2 warnings/72hSprint evidenceADS Q3 W35 - 31 Aug-04 Sep · To Do · finalized_registry ADS Q3 W36 - 07-11 Sep · To Do · finalized_registry | Bug | Jira | 2 | 2 | 2 | Original not recorded | In Progress |
ADS-9032 · [Prod] - Eroare la emiterea adeverintei de absolvireSprint evidenceADS Q4 W40 - 05-09 Oct · In Progress · finalized_registry ADS Q4 W41 - 12-16 Oct · In Progress · finalized_registry | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-9212 · [ANMGD-CLUJ] - Eroare la import studentiSprint evidenceADS Q4 W42 - 19-23 Oct · To Do · finalized_registry ADS Q4 W43 - 26-30 Oct · To Do · finalized_registry | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-9315 · [Prod][TUIASI][rooms-api] Failing health probe restarts PHP-FPM and removes the only endpointSprint evidenceADS Q4 W43 - 26-30 Oct · To Do · finalized_registry ADS Q4 W44 - 02-06 Nov · In Progress · finalized_registry | Bug | Jira | 2 | 2 | 3 | Original not recorded | Done |
ADS-9410 · [Prod][TUIASI] Eight deployments simultaneously lose all available replicasSprint evidenceADS Q4 W44 - 02-06 Nov · To Do · finalized_registry ADS Q4 W45 - 09-13 Nov · To Do · finalized_registry | Bug | Jira | 2 | 2 | 2 | Original not recorded | To Do |
University · Story + Improvement
| Ticket and evidence | Type | Monday | Finish carryovers | Longest run | Planning appearances | Original stack effort | Current status |
|---|---|---|---|---|---|---|---|
ADS-7890 · [BE PHP][Cazari] - Stingerea obligatiilor din E-taxeSprint evidenceADS Q2 W24 - 15-19 Jun · In Progress · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · In Progress · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · Ready for testing · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · Ready for testing · jira_history_reconstruction ADS Q3 W28 - 13-17 Jul · Ready for testing · jira_history_reconstruction | Story | Monday | 5 | 5 | 6 | BE S (2d) Current: BE S | Done |
ADS-8679 · Refactor student, situatie scolaraSprint evidenceADS Q4 W42 - 19-23 Oct · Testing · finalized_registry ADS Q4 W43 - 26-30 Oct · Testing · finalized_registry ADS Q4 W44 - 02-06 Nov · Testing · finalized_registry ADS Q4 W45 - 09-13 Nov · Ready to merge · finalized_registry | Story | Monday | 4 | 4 | 8 | Original not recorded Current: FE S, Java M | Merged |
ADS-7495 · [FE/BE][Adeverinte absolvire] - Creare Probe evaluareSprint evidenceADS Q2 W25 - 22-26 Jun · Code Review · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · Code Review · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · Code Review · jira_history_reconstruction | Story | Monday | 3 | 3 | 10 | FE S (2d) | Done |
ADS-7496 · [FE/BE][Adeverinte absolvire] - Probe&medie pe situatie scolaraSprint evidenceADS Q2 W25 - 22-26 Jun · Code Review · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · Code Review · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · Code Review · jira_history_reconstruction | Story | Monday | 3 | 3 | 10 | FE M (5d) | Done |
ADS-8058 · [BE/FE][UNI] - Generare serii si ani universitari bulkSprint evidenceADS Q3 W29 - 20-24 Jul · In Progress · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · In Progress · finalized_registry ADS Q3 W31 - 03-07 Aug · In Progress · finalized_registry | Story | Not matched | 3 | 3 | 4 | Original not recorded | Done |
ADS-6142 · [Registre Matricole] -US1.1 Creare volume si asociere studenti incadratiSprint evidenceADS Q3 W31 - 03-07 Aug · In Progress · finalized_registry ADS Q3 W32 - 10-14 Aug · Code Review · finalized_registry | Story | Monday | 2 | 2 | 6 | BE M (5d); FE M (5d); Java S (2d) Current: BE M, FE M, Java S | Done |
ADS-7375 · [BE/FE] - Disciplinele in EN pentru programele de studiu din ENSprint evidenceADS Q2 W21 - 25-29 Mai · Code Review · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · Code Review · jira_history_reconstruction | Story | Not matched | 2 | 2 | 4 | Original not recorded | Done |
ADS-7534 · [FE/BE][Adeverinte absolvire] - Flow generare adeverinteSprint evidenceADS Q3 W29 - 20-24 Jul · Ready for testing · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · Ready for testing · finalized_registry | Story | Monday | 2 | 2 | 9 | Original not recorded | Done |
ADS-7535 · [FE] - Download Adeverinta de absolvireSprint evidenceADS Q3 W29 - 20-24 Jul · Ready for testing · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · Ready for testing · finalized_registry | Story | Monday | 2 | 2 | 5 | FE M (5d) Current: FE S | Done |
ADS-8023 · [BE/FE][Adeverinte] Permisiuni &feature flagsSprint evidenceADS Q3 W29 - 20-24 Jul · To Do · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · Ready for testing · finalized_registry | Story | Monday | 2 | 2 | 3 | BE S (2d); FE S (2d) Current: BE S, FE S | Done |
ADS-8584 · [Asachi]-Adaugare ,,Status student" in Clasamentul studentilor din modulul Statistici si rapoarteSprint evidenceADS Q4 W41 - 12-16 Oct · To Do · finalized_registry ADS Q4 W42 - 19-23 Oct · To Do · finalized_registry | Improvement | Not matched | 2 | 2 | 3 | Original not recorded | Done |
ADS-8753 · Calcul credite in functie de nr total credite la disciplinele impuseSprint evidenceADS Q4 W42 - 19-23 Oct · To Do · finalized_registry ADS Q4 W43 - 26-30 Oct · To Do · finalized_registry | Improvement | Not matched | 2 | 2 | 3 | Original not recorded | Done |
ADS-9187 · Adauga forme de finantareSprint evidenceADS Q4 W44 - 02-06 Nov · In Progress · finalized_registry ADS Q4 W45 - 09-13 Nov · Ready to merge · finalized_registry | Story | Not matched | 2 | 2 | 2 | Original not recorded | Merged |
ADS-9384 · Adauga view IBAN pt studenti in modulul de burseSprint evidenceADS Q4 W44 - 02-06 Nov · Ready for testing · finalized_registry ADS Q4 W45 - 09-13 Nov · Ready to merge · finalized_registry | Story | Not matched | 2 | 2 | 2 | Original not recorded | Merged |
Mobile · Bug + Task
| Ticket and evidence | Type | Monday | Finish carryovers | Longest run | Planning appearances | Original stack effort | Current status |
|---|---|---|---|---|---|---|---|
ADS-5808 · [MOB][Wellbeing] - Parintele nu poate vizualiza testele de autocunoastere pe mobSprint evidenceADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction ADS Q3 W28 - 13-17 Jul · To Do · jira_history_reconstruction ADS Q3 W29 - 20-24 Jul · To Do · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · To Do · finalized_registry ADS Q3 W31 - 03-07 Aug · To Do · finalized_registry ADS Q3 W32 - 10-14 Aug · To Do · finalized_registry ADS Q3 W33 - 17-21 Aug · To Do · finalized_registry | Bug | Jira | 12 | 12 | 13 | Original not recorded | Done |
ADS-6990 · [MOB] - Mesaj gresit la stergerea unei note mai vechi de 24 oreSprint evidenceADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction | Bug | Jira | 2 | 1 | 4 | Original not recorded | Done |
Mobile · Story + Improvement
| Ticket and evidence | Type | Monday | Finish carryovers | Longest run | Planning appearances | Original stack effort | Current status |
|---|---|---|---|---|---|---|---|
ADS-8298 · [Elev][Parinte] - Redesign - GradiniteSprint evidenceADS Q3 W32 - 10-14 Aug · To Do · finalized_registry ADS Q3 W33 - 17-21 Aug · To Do · finalized_registry ADS Q3 W34 - 24-28 Aug · To Do · finalized_registry ADS Q3 W35 - 31 Aug-04 Sep · In Progress · finalized_registry | Story | Not matched | 4 | 4 | 4 | Original not recorded | Done |
ADS-8404 · [Elev][Parinte] - Redesign - RapoarteSprint evidenceADS Q3 W35 - 31 Aug-04 Sep · In Progress · finalized_registry ADS Q3 W36 - 07-11 Sep · In Progress · finalized_registry ADS Q3 W37 - 14-18 Sep · Code Review · finalized_registry ADS Q3 W38 - 21-25 Sep · Merged · finalized_registry | Improvement | Not matched | 4 | 4 | 6 | Original not recorded | Done |
ADS-9080 · Create unit testing for Reports, Subjects, Activites, NewsfeedSprint evidenceADS Q4 W40 - 05-09 Oct · In Progress · finalized_registry ADS Q4 W41 - 12-16 Oct · Testing · finalized_registry ADS Q4 W42 - 19-23 Oct · Testing · finalized_registry ADS Q4 W44 - 02-06 Nov · Ready to merge · finalized_registry | Story | Not matched | 4 | 3 | 6 | Original not recorded | Done |
ADS-7141 · [Mob] - Redesign dashboard profesorSprint evidenceADS Q2 W21 - 25-29 Mai · In Progress · jira_history_reconstruction ADS Q2 W22 - 01-05 Iunie · In Progress · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · In Progress · jira_history_reconstruction | Story | Not matched | 3 | 2 | 5 | Original not recorded | Done |
ADS-7807 · [MOB] - Notificări modul admitereSprint evidenceADS Q2 W24 - 15-19 Jun · Ready for testing · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · Ready for testing · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · Ready for testing · jira_history_reconstruction | Story | Monday | 3 | 3 | 5 | Mob M (5d) Current: Mob M | Done |
ADS-8068 · [MOB] - Încheiere situatieSprint evidenceADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction ADS Q3 W28 - 13-17 Jul · To Do · jira_history_reconstruction ADS Q3 W30 - 27-31 Jul · Testing · finalized_registry | Story | Not matched | 3 | 2 | 6 | Original not recorded | Done |
ADS-8997 · [Mobile] - New User Experience PolishSprint evidenceADS Q4 W40 - 05-09 Oct · To Do · finalized_registry ADS Q4 W41 - 12-16 Oct · To Do · finalized_registry ADS Q4 W42 - 19-23 Oct · In Progress · finalized_registry | Story | Not matched | 3 | 3 | 5 | Original not recorded | Merged |
ADS-4419 · [Elev][Părinte] - Redesign - Noutati & ActivitatiSprint evidenceADS Q3 W33 - 17-21 Aug · In Progress · finalized_registry ADS Q3 W34 - 24-28 Aug · In Progress · finalized_registry | Story | Monday | 2 | 2 | 6 | BE S (2d); FE M (5d); Mob L (10d) Current: BE M, FE S, Mob L | Done |
Unassigned · Bug + Task
| Ticket and evidence | Type | Monday | Finish carryovers | Longest run | Planning appearances | Original stack effort | Current status |
|---|---|---|---|---|---|---|---|
ADS-4341 · [Condica de prezenta] - Nu apare butonul ,, semneaza condica pentru toata ziua Sprint evidenceADS Q2 W22 - 01-05 Iunie · To Do · jira_history_reconstruction ADS Q2 W23 - 08-12 June · To Do · jira_history_reconstruction ADS Q2 W24 - 15-19 Jun · To Do · jira_history_reconstruction ADS Q2 W25 - 22-26 Jun · To Do · jira_history_reconstruction ADS Q2 W26 - 29 Jun-03 Jul · To Do · jira_history_reconstruction ADS Q3 W27 - 06-10 Jul · To Do · jira_history_reconstruction | Bug | Jira | 6 | 6 | 7 | Original not recorded | Canceled |
Unassigned · Story + Improvement
| Ticket and evidence | Type | Monday | Finish carryovers | Longest run | Planning appearances | Original stack effort | Current status |
|---|
How the figures were computed
Unavailable current Jira issues retained using preserved historical evidence: ADS-8684 · current Jira issue unavailable. No inaccessible issue is removed using stale negative work evidence.
The six-month window ends at the latest canonical weekly boundary. We include sprints whose outcome overlaps the window; only completed outcomes count as misses. Frozen finalized rows take precedence over complete Jira history reconstruction, including frozen planning absences. Distinct tickets with at least two Finish carryovers form the repeated cohort. Group by the latest eligible Finish-planning team and current Jira type. Canceled rows and workflow/outcome conflicts keep their existing metric treatment.
Platform/Infra and Rojan exclusions apply across the whole ticket: current assignment or any planning assignment/work stream in the study window excludes it. Previously reviewed exclusions remain protected as history grows. The comparison also checks frozen assignment/work-stream values across its entire history.
Both Finish views use their immutable source issue sets, then the same exclusions. Planned-only counts original Finish promises. Overall unions eligible additions marked Finish at outcome; historical admission intent is not fully available. An unfinished To Do item is removable only before recorded work: parent/child active statuses, frozen active states, time/worklogs and observed code/MR evidence protect it. Keep its first-work calendar week and later. Strict requires a later observed start. Cleanup additionally includes still-unstarted and later-canceled unstarted work. Completed counts never change.
Pool counts before dividing; do not average weekly/team percentages. Team overlaps can make summed team counts exceed the deduplicated organization count. No recorded work is not proof of zero work. This retrospective denominator simulation does not establish extra throughput or a causal improvement. Right-censored historical classifications may change as later starts become visible; source revisions and evidence-read timestamps are archived with each run.
Monday membership is a current board capture, not proof of historical absence. Original sizes come only from the preserved reviewed estimate history. New sizes are current-only until historical evidence exists. Per stack, S=2d, M=5d, L=10d; XL is unmapped. These are effort days and cannot be added into calendar lead time. Historical size capture is 2026-10-29.
ADS Jira board · Monday board · Refresh/source receipt. Raw histories, personal account IDs and local paths stay private.